Saguaro Cliffs
Observatory - Construction
|
Welcome. The
following pages chronicle the construction of the Saguaro Cliffs
Observatory
|
Day 1 - 31 July 2009
|
Click each picture for a full
size version |
|
The tractors begin grubbing
of the area for the observatory |
|
|
We need
to save these Saguaro's.
|
|
|
There's no turning back
now. |
|
|
Day 4 -
August 3, 2009 |
Click each picture for a full size version |
|
First
Layer of Fill |
|
|
The
Observatory Area
|
|
|
Day 6 -
5 August 2009 |
Click each picture for a full size version |
|
Pier #2
Goes Here |
|
|
Laying out the pad so we
know where the yard walls
go |
|
|
The
digging begins |
|
|
The yard
wall footer is dug |
|
|
Day 7 -
6 August 2009 |
Click each picture for a full size version |
|
Preparing to dig the pier footers |
|
|
7 August
2009 |
Click each picture for a full size version |
|
9 August
2009 |
Click each picture for a full size version |
|
2 Pier
Footers and the garden wall footers |
|
|
The
garden wall footers
|
|
|
12
August 2009 |
Click each picture for a full size version |
|
The wall
takes shape |
|
|
Preparing to remove the existing wall |
|
|
The soon
to be East wall |
|
|
13
August 2009 |
Click each picture for a full size version |
|
14
August 2009 |
Click each picture for a full size version |
|
19
August 2009 |
Click each picture for a full size version |
|
20
August 2009 |
Click each picture for a full size version |
|
21
August 2009 |
Click each picture for a full size version |
|
We have
a form!
Note the "3 blocks in the ground" Observatory in the foreground |
|
|
The
beginning of a modified Skyshed |
|
|
The
observatory setting |
|
|
26
August 2009 |
Click each picture for a full size version |
|
Sighting
the Piers |
|
|
27
August 2009 |
Click each picture for a full size version |
|
Sighting
the True North lines |
|
|
Closeup
of the "around the rebar" sight lines.
Note the "behind the pier"
markers. |
|
|
Once the
Sonotube is set, the string is extended to the rear markers to
complete the lines. |
|
|
29
August 2009 |
Click each picture for a full size version |
|
Pier Base Pouring Day!
Preparing the J-Bolts |
|
|
Preparing the templates |
|
|
The
completed templates |
|
|
Preparing the sonotubes |
|
|
Trimming
the rebar |
|
|
The
sonotubes are set |
|
|
Mixing
the first batch of concrete. Each pier required two, 40 lb
bags |
|
|
The
supervisor shows up... |
|
|
The
first shovel of concrete |
|
|
Vibrating the air out |
|
|
Setting
the rear sight line |
|
|
Inserting the first j-bolt template |
|
|
Picture
perfect, pier #1 |
|
|
Picture
perfect, pier #2 |
|
|
Closeup
of pier #2 template |
|
|
We have
piers! |
|
|
31
August 2009 |
Click each picture for a full size version |
|
The wall
gets its first coat of stucco |
|
|
Naked
piers |
|
|
1
September 2009 |
Click each picture for a full size version |
|
Rockite
icing |
|
|
Rockite
icing |
|
|
Forms
removed, Rockite trimmed and the bolts cleaned |
|
|
Cleaned
bolt |
|
|
The
completed pier base with the safety devices in-place |
|
|
The
garden wall with the final coat of stucco and the completed pier
bases.
Waiting for the final
fill to be added and the slab to be poured... |
|
|
8
September 2009 |
Click each picture for a full size version |
|
A fresh
coat of paint on the wall |
|
|
12
September 2009 |
Click each picture for a full size version |
|
.
SLAB POURING DAY!
We have 4 1/2 yards
of concrete |
|
|
Setting
the pier base sleeves |
|
|
The pier
base sleeves are in place |
|
|
One Bob
Cat at a time |
|
|
May I
have another, please? |
|
|
The HARD
part of the job |
|
|
Nice
screed |
|
|
The
Artistry begins |
|
|
Need one
more half bucket |
|
|
Looking
good |
|
|
The
Lucky Dollar |
|
|
The
Telescope Room |
|
|
Picture
perfect |
|
|
Watching
concrete cure |
|
|
16
September 2009 |
Click each picture for a full size version |
|
Still
watching concrete cure |
|
|
The sand
isolation layer and the Sonotube |
|
|
The
observatory setting, slightly improved... |
|
|
17
September 2009 |
Click each picture for a full size version |
|
A view
of the observatory pad looking over the recently started home
addition... |
|
|
25
October 2009 |
Click each picture for a full size version |
|
Checking
out the Observatory location and the wall height.
Performing an
eyepiece comparison test using the 13.1 inch Odyessy 1.
|
|
|
31
October 2009 |
Click each picture for a full size version |
|
Time to
remove the Sonotube and the sand.
|
|
|
Since
the sand depth was 20 inches, and the crevice tool was only 8
inches long, can anyone say Apollo 13? A little garden hose and
some duck tape did the trick. |
|
|
The sand
is out and it's time to pull the Sonotube out of the hole. |
|
|
And...
out comes the Sonotube |
|
|
And 4
1/2 hours later, we have 2 cleaned pier bases waiting for the
foam insulation... |
|
|
1
November 2009 |
Click each picture for a full size version |
|
Time to
stain the concrete... |
|
|
Finished...
|
|
|
5
November 2009 |
Click each picture for a full size version |
|
The
stain is dry and has darkened up a bit... |
|
|
5
November 2009 |
Now we wait for the Media Room addition to be completed in about
3 weeks before proceeding with the observatory building
construction |
|
|
|